Laying floor tiles: full bed, spacers and the tap test

Published 25 November 2026

Site & quality guide from the BHK99 knowledge centre
Site & quality guide from the BHK99 knowledge centre

Tap the tile - a solid sound means good work, a hollow sound means do it again. Why dabs of mortar crack tiles, how back buttering and a notched trowel give a full bed, and the spacers and clips that keep edges flush and joints straight.

A floor tile fails from underneath. If there is empty space under it - because the mason placed dabs of mortar at the corners instead of a full bed - the tile sounds hollow when tapped, and sooner or later it cracks under a dropped pan or a heavy step. The whole craft of tiling is making sure there is no void under any tile.

The method is adhesive spread with a notched trowel on the floor, plus a thin layer on the back of the tile itself - back buttering (IS 15477). Joints are kept even at 2-3 mm with spacers, and on large tiles leveling clips pull neighbouring edges flush so there is no lippage to stub a toe on.

Two mistakes that cannot be fixed later

  • Dabs instead of a bed: mortar only at the corners leaves the centre hollow - the tap test exposes it immediately, cracks expose it eventually. Spread evenly with a notched trowel and butter the tile's back.
  • No spacers, joints by eye: lines wander and edges sit proud. Use a string line, spacers in every joint, and check level every 2-3 tiles.

The right sequence, in six steps

  • Start from the room's centre line, set out with string.
  • Spread adhesive over small areas with a notched trowel.
  • Back-butter each tile with a thin, even layer.
  • Set the tile and tap it down with a rubber mallet.
  • Fit spacers and leveling clips; check level as you go.
  • After it dries, tap every tile - replace any that sound hollow.

Numbers worth remembering

  • Joint width on vitrified tiles: about 2-3 mm
  • Adhesive bed: about 3-6 mm (IS 15477)
  • Lippage between tiles: under about 1 mm
  • Walking on the new floor: about 24 hours, per the adhesive
  • Tap test: every tile, no exceptions

Site checklist

  • Set out from the centre; adhesive full and notched
  • Back buttering done; a spacer at every joint
  • Leveling clips on large tiles; level checked every few tiles
  • Hollow-sounding tiles relaid before grouting

This guide is adapted from BHK99's illustrated site handbook series. Finish the job properly with grout and joints, and see the wall version in wall tiles done straight.

Project Enquiry

Tell us about your construction requirements and our team will get in touch.

Our Locations

We serve key locations with a local, on-ground approach.