A beam bends downward in the middle, so its main steel sits at the bottom - and shear is highest at the columns, so stirrups sit closest there. The patient part comes after casting: props stay for weeks, and removing them early is how beams sag.
Beams are the horizontal bands between columns - they collect the slab load and pass it into the columns. A beam bends downward in the middle of its span, so the tension is at the bottom and the main steel sits in the bottom layer, with extra bars over the supports where the bending reverses.
The second thing a beam cares about is shear, and shear is highest right next to the columns. That is why stirrups are placed close together - within a length of twice the beam depth from the column face, at a spacing of d/4 or as the drawing says (IS 13920:2016) - and a little wider in the middle. Stirrups spaced equally along the whole beam are a classic site shortcut, and the diagonal cracks near supports are its signature.
Two mistakes that cannot be fixed later
- Stirrups equally spaced throughout: weak exactly where shear is highest. Read the drawing's spacing separately for the ends and the middle.
- Weak wooden poles with no base: crooked timber standing directly on loose soil sinks under the casting weight, and the beam sags - or the shuttering collapses. Use straight adjustable props on a wooden base plank, braced to each other, with the level perfectly checked.
The right sequence, in six steps
- Set the beam soffit shuttering level between columns, props and base planks below.
- Place the bottom main steel and stirrups at the drawing spacing.
- Tie the top bars and the extra bars over the supports.
- Fix side shuttering, with cover blocks below and on the sides.
- Cast the beam together with the slab, vibrating the beam properly.
- Side shuttering can open in 24 hours - but props stay for weeks.
Numbers worth remembering
- Cover on beam steel: 20-30 mm depending on exposure (IS 456, Table 16)
- Stirrups near the joint: spacing of d/4 within a 2d length, as per drawing (IS 13920:2016)
- Beam soffit shuttering: 7 days, with re-propping (IS 456, Table 11)
- Props for spans up to 6 m: 14 days (IS 456, Table 11)
- Props for spans over 6 m: 21 days (IS 456, Table 11)
Site checklist before casting
- Soffit level, props straight, a base plank under every prop
- Bottom and top bars as per drawing; stirrups closer near supports
- Extra top bars extending the correct length; cover blocks below and on the sides
- Laps kept out of the column joints
Remove props too early and the beam will sag - give the concrete time to gain strength. This guide is adapted from BHK99's illustrated site handbook series. Continue with the roof slab, or check what to verify before any slab pour.