A roof is cast only once. The main bars run in the shorter direction, the top steel stands on chairs that workers must not flatten, the conduits sit between the two layers - and then the slab is flooded with water for a week. Here is the whole picture.
The roof slab is the one element of the house that is cast in a single day and seen from below for decades. Everything that matters - the two layers of steel, the electrical conduits, the cover, the level - must be right before the concrete arrives, because a roof is cast only once.
A slab bends more in the direction of its shorter span, so the main bars run in that direction, in the bottom layer. Near the beams the bending reverses, which is why extra top bars sit over the supports - held at their correct height by steel chairs.
Two mistakes that cannot be fixed later
- Walking on the top steel: with no chairs, workers walking on the mesh press the top bars down, and the slab's strength over the supports is quietly lost. Use steel chairs to fix the height, and walk only on wooden planks laid over the steel.
- Conduits below the mesh: an electrical pipe laid directly on the shuttering destroys the bottom cover, and cracks and damp patches follow years later. The bottom mesh sits on cover blocks; the conduits and junction boxes are tied above it, between the two layers.
The right sequence, in six steps
- Shuttering plates level, a grid of props below, no gaps at the joints.
- Bottom mesh - main plus distribution bars - on cover blocks.
- Electrical conduits and fan/light boxes tied above the mesh.
- Extra top bars near the beams, standing on steel chairs.
- Cast the whole slab in one go; level with a vibrator and straight edge.
- From the next day, build small bunds and pond water on the slab for 7-10 days.
Numbers worth remembering
- Cover on slab steel: 20 mm mild / 30 mm moderate exposure (IS 456, Table 16)
- Main bar spacing: not more than 3d or 300 mm (IS 456, 26.3.3)
- Distribution bar spacing: not more than 5d or 450 mm (IS 456, 26.3.3)
- Slab soffit shuttering: 3 days with re-propping (IS 456, Table 11)
- Curing by ponding: 7-10 days
Site checklist before the pour
- Shuttering level and tight, props on base planks
- Main bars in the shorter direction, bottom layer, on cover blocks
- Conduits between the layers, boxes resting on the mesh
- Top bars on chairs; planks laid for walking
- Curing arrangement ready before the pour, not after
Fix the steel, the pipes and the level - all three - before casting. This guide is adapted from BHK99's illustrated site handbook series; pair it with our hold-point checklist for the day before the pour, and see concrete quality checks for the mix itself.