Concealed pipes: straight chases, clamps and the pressure test

Published 25 November 2026

Site & quality guide from the BHK99 knowledge centre
Site & quality guide from the BHK99 knowledge centre

Test first, plaster later - do it the other way and the wall gets built twice. The one-third rule for chase depth, a clamp every metre, outlets set level for the tile, and a gauge that must hold pressure for thirty minutes before anything is covered.

Once a water line disappears into the wall, every mistake in it becomes a demolition job. The concealment itself has rules - how the chase is cut, how the pipe is held, how outlets sit - and one non-negotiable gate at the end: a pressure test, passed and photographed, before a trowel of plaster goes anywhere near the line.

The chase comes first. Cut it straight with a wall chaser - two parallel lines, the middle removed with a chisel - and never deeper than about one-third of the wall thickness, or the wall itself is weakened. Hammering a crooked channel shakes the surrounding bricks loose and almost always goes too deep.

Two mistakes that cannot be fixed later

  • A crooked chase broken out with a hammer: deep, ragged, and damaging to the wall around it. Two straight cutter lines, chisel out the middle.
  • Plastering without a test: the leak announces itself after the tiles are on. Fill the whole line with water, pump it to pressure, and watch the gauge for 30 minutes - it must not drop.

The right sequence, in six steps

  • Mark the route on the wall with chalk, matching the drawing.
  • Cut the chase with a chaser, depth limited to a third of the wall.
  • Set the pipe with a clamp about every metre.
  • Set tap and mixer outlets at the right height, dead level, allowing for tile thickness.
  • Pressure test: fill, pump, and hold for 30 minutes on the gauge.
  • Only after a pass: fill the chase with mortar and plaster over mesh.

Numbers worth remembering

  • Chase depth: not more than about 1/3 of the wall thickness
  • Clamp spacing: about 1 m
  • Test pressure: about 1.5 times the working pressure (NBC / manufacturer)
  • Test duration: at least 30 minutes without a drop
  • Mesh over the filled chase: about 75 mm each side

Site checklist

  • Route matches the drawing; chase straight, cut not hammered
  • No RCC column or beam ever cut for a pipe
  • A clamp every metre; outlets level and at the right height
  • Pressure test passed; photographs taken before filling

Test first, plaster later. This guide is adapted from BHK99's illustrated site handbook series. The wall is closed with crack-free plaster; the fixtures that land on these outlets are in bathroom fittings heights.