String, level and plumb - use all three daily and the wall never goes crooked. The bond that stops cracks, the mortar ratios for thick and thin walls, why a wall rises only a metre a day, and the curing that makes mortar actually strong.
Laying bricks looks simple, which is exactly why it is done badly so often. A straight, strong wall comes from four habits used together every single day: a string line for the course, a spirit level across, a plumb for the vertical, and a correct bond so the bricks tie into each other.
The joints matter as much as the bricks. Brick joints should be about 10 mm, even everywhere and fully filled (IS 2212). The mortar is commonly 1:6 cement-sand for a normal 230 mm wall and a richer 1:4 for a thin 115 mm partition.
Two mistakes that cannot be fixed later
- Vertical joints stacked in a line: the wall behaves like two separate halves, and a crack runs straight down the stacked joints. In a correct bond, every vertical joint sits over the middle of the brick below.
- Thick, hollow joints: crooked bricks or plain hurry produce 20-25 mm joints with gaps inside - a path for water and cracks. Spread a full bed of mortar, press each brick lightly into place, and keep joints near 10 mm.
The right sequence, in six steps
- Lay the first course on the plinth against a chalk line and string.
- Measure cement and sand with a gauge box and mix properly.
- Lay each brick on a full mortar bed, frog up.
- Check level and plumb every 3-4 courses.
- Stop at about one metre of height per day, leaving the ends stepped - fresh mortar below cannot carry more.
- From the next day, cure the wall with water for 7 days.
Numbers worth remembering
- Joint thickness: about 10 mm (IS 2212)
- Mortar for a 230 mm wall: 1:6; for a 115 mm wall: 1:4
- Height in a day: not more than about 1 m (IS 2212)
- Curing: at least 7 days (IS 2212)
Site checklist
- First course straight to the string; mortar measured with a gauge box
- Bricks soaked, laid frog up; vertical joints never in a line
- Joints about 10 mm and fully filled
- Level and plumb checked every 3-4 courses; 7 days of curing