The ceiling of the room below stays dry only if the bathroom floor holds water back. Rounded fillets at corners, coating carried up the wall, a collar at every pipe - and no tiling until the floor has passed a full ponding test.
Every damp patch on a bedroom ceiling started life as a shortcut in the bathroom above. A bathroom floor is a stack of layers - slab, waterproof coating carried up the walls, filling, sloped screed, then tile - and the coating layer is the one that decides whether the room below stays dry.
Two details carry most of the protection. The coating must climb the wall: at least 300 mm all around, and 1.8-2 m in the shower area. And every corner where floor meets wall gets a rounded cement fillet first, so the coating bends over a curve instead of tearing in a sharp angle.
Two mistakes that cannot be fixed later
- A broken or missing coating at corners and pipes: water finds the one gap and drips through the slab. Floor and wall must be coated as one piece over rounded fillets.
- A gap around the pipe: most bathroom leaks start exactly where a pipe passes through the slab. Fill the joint with non-shrink grout and seal over it with a coating-and-fabric collar.
The right sequence, in six steps
- Clean the floor and walls, remove loose mortar, fix the pipes in place.
- Make fillets at the corners; grout every pipe penetration.
- Apply the coating in two coats, crossed over each other, 300 mm up the wall.
- Block the drain and pond water for 24-48 hours; inspect the ceiling below.
- Only after a pass: light filling, then a screed sloped about 1:100 to the drain.
- Tile and grout without damaging the coating.
Numbers worth remembering
- Coating up the wall: at least 300 mm; shower zone 1.8 m or more
- Coats: at least 2, applied crosswise, per the manufacturer
- Ponding test: 24-48 hours with the drain blocked
- Floor slope: about 1:100 towards the drain
- Sunken depth: as per the drawing
Site checklist
- Surface clean; fillets at every corner; every pipe joint sealed
- Two coats, carried 300 mm up the wall
- Ponding test passed and recorded before any tiling
- Screed sloped to the drain
No tiling without a ponding test - one day of checking buys years of peace. This guide is adapted from BHK99's illustrated site handbook series. The same thinking applies overhead: read terrace waterproofing, and for fixture positions see bathroom fittings heights.